Here is the conversation we have in a lot of Valley kitchens. The cabinets are picked, the quartz is ordered, the contractor has a start date. Somebody asks what the electrical is going to run. And the honest answer is that it depends almost entirely on how many circuits are in that kitchen right now, which nobody has looked at yet.

A modern kitchen needs roughly seven or eight circuits. A kitchen built in Mesa or Chandler in 1988 often has three. That gap is the electrical budget, and it is worth understanding before the demo starts rather than after.

The Short Answer

For a typical all-electric kitchen, the list looks like this:

  • Two 20 amp small appliance circuits for the countertop receptacles. This is a minimum, not a target, and those circuits are not allowed to feed the lights or anything outside the countertop and dining areas.
  • One dedicated circuit for the refrigerator. Technically there is some flexibility here, but in practice every kitchen we wire gets its own fridge circuit, because you do not want a tripped breaker on a weekend away to cost you everything in the freezer.
  • One circuit for the dishwasher, which also needs ground fault protection.
  • One circuit for the garbage disposal. A disposal and dishwasher can share in limited cases, but separating them is cleaner and matches most appliance manufacturer instructions.
  • One dedicated circuit for a built-in microwave, whether it is over the range or in a cabinet.
  • One 240 volt circuit for the range or cooktop, usually 40 or 50 amps. A separate wall oven gets its own.
  • One lighting circuit for the ceiling cans, under-cabinet lighting, and any pendants.

Add a beverage fridge, a pot filler with a heated element nearby, a built-in coffee system, or a steam oven, and the count climbs from there.

What Older Valley Kitchens Actually Have

Go look in your panel. If your house went up in the 1970s or 1980s, the kitchen is commonly running on two small appliance circuits and a shared lighting circuit, and the microwave, the fridge, and sometimes the disposal are all riding on those same two.

That is why a lot of Valley homeowners live with the morning breaker dance: microwave plus toaster plus coffee maker equals a trip. People assume the breaker is weak. The breaker is fine. It is doing exactly what it is supposed to do on a circuit carrying three appliances that were never meant to share.

A remodel is the moment that gets fixed, because the walls are open and adding a circuit is a fraction of what it costs to fish one later.

Ground Fault and Arc Fault Protection

Two things have changed significantly over the last few code cycles and both will show up in your remodel.

GFCI protection has expanded a lot. It used to be countertop receptacles only. Recent code has pushed it well past that, into the dishwasher circuit and, in newer cycles, essentially every receptacle in the kitchen including the 240 volt ones. What your specific city enforces depends on which code cycle they are on, which is one of several reasons this is not a great place to work from a YouTube video. If you want the basics of how the device itself works, we wrote up how GFCI outlets work and how they are wired.

Arc fault protection applies to most of the rest. Arc fault breakers look for the signature of an arcing connection, which is the thing that actually starts electrical fires inside walls. In a remodel, new circuits generally get it.

The practical effect is that a modern kitchen panel has a lot more protective breakers in it than a 1985 panel did, and those breakers take space. Which leads to the part people do not expect.

The Panel Is Usually the Real Question

You cannot add five circuits to a panel that has no room and no capacity. On a lot of Valley remodels, the kitchen is the project and the panel is the actual cost.

Two separate issues:

Space. Physical slots for breakers. Tandems can sometimes buy a little room, but plenty of panels are already full of them.

Capacity. Whether the service itself can carry the new load. Going from a gas range to an induction cooktop, for instance, adds a serious 240 volt load that was not there before. So does adding a wall oven, and so does an EV charger somebody wants in the garage as part of the same project.

If the panel needs to come up, a like-for-like 200 amp replacement generally runs $5,200 to $6,500, or $6,400 to $8,750 when the meter base and panel are replaced together as an all-in-one. Our guide to the signs you need a panel upgrade covers what to look for, and the panels page has the details of the work.

Find this out in week one. The worst version of a kitchen remodel is the one where the cabinets are installed and then somebody discovers the induction cooktop has nowhere to land.

Outlet Placement, Islands, and the Details That Get Missed

Countertop receptacle spacing is governed so that no point along the counter is very far from a receptacle, which in practice means an outlet every few feet along any usable counter run, and any counter section a foot or wider gets one. It is a rule that exists so people stop running cords across sinks and cooktops.

Islands are the part that has genuinely moved across recent code cycles, and different Valley cities are on different cycles. The safe approach on an island is to plan for accessible power, get it designed with your electrician rather than assumed, and avoid the old trick of a receptacle mounted face up in the counter or tucked underneath where a cord can be pulled. Those have fallen out of favor for good reasons.

Other things that get missed constantly in remodels:

  • Under-cabinet lighting needs a switched circuit and a plan for where the driver and wiring hide. Decide before the backsplash goes on.
  • Recessed lighting layout is worth doing properly rather than putting cans on a grid. We covered the approach in our post on recessed lighting installation in Phoenix.
  • The range hood. A big hood needs its own circuit and a real duct run, not a recirculating filter, if you actually cook. Ductwork is not our trade, and it is the one part of a kitchen where we hand people to our sister company The Cooling Guy HVAC (Arizona ROC 364481) rather than guess.
  • Appliance garages and drawer microwaves need a receptacle located exactly where the cabinet maker expects it. Get the appliance specs before rough-in.

Going Gas to Induction

This comes up more every year, and it is straightforward as long as it is planned. An induction cooktop needs a dedicated 240 volt circuit, commonly 40 or 50 amps depending on the unit, run from the panel to the cooktop location.

The catch is that a gas kitchen was never wired for it. There is no existing 240 volt circuit behind that cabinet, so it is a new run plus a new breaker plus panel space, and it is exactly the sort of thing that is easy during demo and painful afterward. If induction is even on your list of maybes, run the circuit while the walls are open. An unused 240 volt circuit behind a cabinet is cheap insurance.

Timing: When the Electrician Should Be There

Kitchen remodels go well when the electrical happens in this order:

  1. Before design is locked. Panel evaluation and a load calculation. This tells you whether a panel upgrade is in the budget.
  2. After appliances are selected, before rough-in. Every circuit, receptacle location, and switch leg is decided off the actual appliance specs and the cabinet drawings.
  3. Rough-in with the walls open. New circuits, boxes, lighting, and any panel work.
  4. Trim out. Devices, fixtures, under-cabinet lighting, appliance connections, and testing.

The kitchens that get expensive are the ones where somebody tried to reuse existing circuits to save money and ended up with a brand new kitchen that still trips a breaker when the toaster and the air fryer run at the same time.

When to Call Us

Call us if you are planning a kitchen remodel and want to know what the electrical will require before you commit to a budget, if your current kitchen trips breakers when you run two appliances, if you are switching from gas to induction or adding a wall oven, if your contractor needs a licensed electrician for rough-in and trim, or if you just want somebody to open the panel and tell you honestly whether it can handle what you are planning.

We are happy to walk a kitchen before you are committed to anything. It is a lot easier to plan around a panel upgrade than to discover one mid-project.

At The Wire Guy Electric (Arizona ROC 365306), we handle remodel wiring and dedicated circuits as a family-owned electrical contractor, and we work alongside your cabinet and countertop trades rather than against their schedule.

We serve Mesa, Scottsdale, Gilbert, Chandler, Tempe, Queen Creek, Paradise Valley, and Fountain Hills. Request a free estimate and we will price the electrical side of your kitchen before demo day.

We're ready to work for you

🟢 Free estimates available